Ever closer...
We almost have our "air moving" equipment installed (upper left)...tomorrow should finish up the instal...
The kitchen cabinets have been moved out to be flush with the refer and the counter will cover the top to the wall...
Stained trim is being installed in the foyer...you are getting an advance peek, the beams and the floor will be stained the trim color...
The "exhibit ledge" in the foyer is being trimmed out...
Just this afternoon the crew from "Asplendah" (tree trimmers) stopped by to scope out the job they will begin next Wednesday...
Interior doors are to arrive in the next day or so...when they are hung and the baseboard is installed the floor guys will return to sand, stain and finish the floors...
OK, I'm now getting too far ahead of myself and certainly don't want to spoil the surprises that lay in store over the next couple of weeks...
Happy guessing...
Mike, I will give a guess of August 6 as your move in date if you don't hit any snags.
ReplyDelete