Barb and I have begun the process of building an addition to our Cottage. The blog will be a visual and written journal of the progress. There may not be a daily entry but as progress is made posts will be made frequently. Estimates for completion are from four to eight months.
Thursday, March 8, 2012
Day 134
Up, up, up in the air...
The structure makes its way higher and higher with the framing of the second story.
I took a walk to the pier today and looked back to the house (cottage). Now that the framing is above the existing roof the building is beginning to look like the elevations in the drawings.
More lumber arrived today with more framing lumber and the roof rafters...finishing the plywood walls and putting the "Tyvek" on as the skin will be next, then the rafters and felt paper....windows installed and we will be "under roof."
Stay tuned...